Pre Preparations
RM PP
DRA
PRE-RA MEETING
RA MEETING WITH CUSTOMER
STYLE LOADING
-35 Days
BEFORE PDRA
PDRA
PRODUCT DEVELOPMENT TRIAL LINE
-30 Days
PROVISIONAL STITCHING
PROVISIONAL FEEDBACK INTERNAL
PROVISIONAL FEEDBACK-EXTERNAL
TLT CATEGORY 1
-12 Days
PRE FI PREPARATION
PRE FI SEWING
-11 Days
CUTTING INTEGRATION
MOLDING INTEGRATION
-10 Days
SEWING INTEGRATION
SEWING INTEGRATION FEEDBACK-INTERNAL
-7 Days
Sewing Integration Feedback - To development team
-5 Days
Pre-FI Conclusion
-4 Days
Integration Conclusion Meeting
Knowledge Transfer Meeting (CC)
-2 Days
Preparation for Trial Line
-1 Days
Trial Line (Plant)
TLT Category 2 (If required)
Delivering cuts for sub contract activities
3 to 0 Days Prior PP
3 Days Prior PP - Preparation for Bulk production
2 Days Prior PP - Preparation for Bulk production
1 Day Prior PP - Preparation for Bulk production
0 Days (PP)
PP meeting (3 Days prior PSD)
Pilot Stitching (If required)
Pilot appraisal meeting (If required)
1 Day
Preparation activities
Preparation activity (1 day after PP / 2 days prior PSD)
2 Days
Preparation activity (2 days after PP / 1 day prior PSD)
3 Days
QCO Cut Kit and Trims (6 hours Prior to Line Feeding)
5 hours Prior to Line Feeding
4 hours Prior to Line Feeding
3 hours Prior to Line Feeding
2 hours Prior to Line Feeding
1 hour Prior to Line Feeding
Pre-feeding meeting before 30 mins
Line Feeding
1st 10 pcs review meeting
4th hour, 1st Day
100 pcs offering (VS&CO Only)
2nd day
3rd day
Total bulk cut approval (VS&CO Only)
First 3 days
Bulk Production & Shipment
Bulk consumption confirmation
Bulk Production
Carton Pull
Bulk Verification
Shipment Preparation
Shipment Verification (Final Inspection / CNI / Customer / Third
party)
Shipment Loading